Okay. Here is the update. This has been going on since late May and we still live on a dirt road. Three weeks ago Judy talked with the contractor who told her then that our section would be done in 2-3 weeks. I guess they missed. Twice they have removed newly poured cement curbing and poured it again. The last time was because they forgot the handicap access curbs at the corners. Our section is the easiest part of the whole project and only 1/3 of it. It is supposed to be done before November.

They brought out the big equipment today. Should get a lot done now. Well actually, they did have the road-grader out and they scrapped off and removed 4-5 inches of dirt, but there is still dirt there. I was hoping that they would find a new road under there. But today they have done more work on the road than they have done in several days. But 2/3 of the project still needs to be done and there is only 2 1/2 months left, half way through their time table. Maybe they will be done before the 2011 Earle Brown Days Parade.